51) Given the following chart of jobs assigned with Johnson’s rule, suppose that all the jobs (A, B, C, etc) could be evenly divided into two tasks (such as A1 and A2, B1 and B2, etc). Suppose job B is divided into jobs B1 and B2, each with a body work time of 4.5 hours and a paint time of 2 hours. How much is makespan reduced by this splitting of B? 52) Given the following chart of jobs assigned with Johnson’s rule, suppose that all the jobs (A, B, C, etc) could be evenly divided into two tasks (such as A1 and A2, B1 and B2, etc). Suppose job D is split into two equivalently sized sections, D1 and D2, each with a body work time of 1.5 hours and a paint time of 2 hours (D1 and D2 sum to 3 hours of body work and 4 hours of paint which is equivalent to D). How much is makespan reduced by this splitting of D? 53) Complete the table; find average lateness, average completion time, and average number of jobs in the system. Assume all durations are in days and that the jobs are processed at the shop in the order that they arrive (A then B then C then D). Job Process Time Flow Time Due Date Lateness A 5 Â 7 B 3 Â 9 C 2 Â 12 D 5 Â 4 Sum (Average) 15 (3.75) Â XXXXX